VFD technology ideally lends itself to customer specified designs and patterns. Its unique construction enables customers to specify custom announciators and icons in a cost effective manner. Home appliances, audio, video and measuring equipment manufacturers have all used this low cost feature to offer their customers very attractive and efficient displays which greatly improves their functionality and marketing appeal.
Design Procedure
Customer
Noritake (ISE Electronics Corp.)
1. Request for Quotation With your rough design and request
2. Feasibility Study upon customer's design 1. Outer dimensions
2. Display patterns (outline sketch)
3. Electrical specification
4. Quality and reliability standard
5. Production Schedule (quantity, time scale etc.)
3. Proposal Drawing (Sketch) and Price Quote
4. Receipt of Sketch and Quotation
Re-examined ( back to 3 if necessary )
5. Pattern Data and Request for Spec Presentation of precise CAD data of display pattern.
DXF format is most preferable.
If can not prepare the CAD data, it will take additional development time.
6. Tentative Specification (spec)
Submitting within one week after receipt of your instruction.
7. Evaluation of Tentative Spec
Re-examined ( back to 6 if necessary )
8. Approval of Tentative Spec And Release of a development order for the engineering samples (E/S).
9. Development of the E/S Normally 5 to 20 pcs. of the first E/S prepared.
General lead-time 40 to 75 days after received your order.
10. Receipt and Evaluation of the E/S Approval for the E/S and Request for Final Spec
Re-examined ( back to 9, 6 or 3 if necessary )
11. Preparation of Final Specification.
12. Approval of Final Specification.
Re-examined ( back to 11 if necessary)
13. Order release for Pre-Production Samples Order for your pilot-run.(200 pcs MAX)
Process 13 to 15 may be omitted.
14. Pre-Production Samples About 40 to 75 days lead-time after receipt your order
15. Evaluation of Pre-Production Samples
Re-examined ( back to 14 if necessary )
16. Order release for Mass Production
17. Mass Production General lead-time for mass production is 75 days.